Timeline
Key stages on our journey
From putting funding in place to progressing Front End Engineering and Design, we are well underway with Viking CCS. We look forward to taking the project further in the coming months and years.
Non-statutory consultations on route corridor
Spring-Autumn 2022

Statutory consultation on preferred route
Winter 2022/23

DCO accepted for examination
November 2023

Anticipated decision by Secretary of State
2025

Construction period to begin
2025

Storage to begin
Planned storage of 10 million tonnes CO₂ per year by 2030